00:00:08:09 - 00:00:08:17
Here.
00:00:08:17 - 00:00:12:07
We'll take a look at the specification
of production restrictions.
00:00:12:24 - 00:00:15:09
So these are a way of allocating
the amount of time
00:00:15:09 - 00:00:20:09
it takes to produce a product
as well as which days
00:00:20:09 - 00:00:23:28
you can and cannot work on the production
of the output.
00:00:24:18 - 00:00:28:09
For example, if your office is shut
on weekends and you'll have nobody around
00:00:28:09 - 00:00:33:04
to operate the machines,
then we don't want that to be included.
00:00:33:29 - 00:00:36:09
Production
restrictions are configured against
00:00:36:09 - 00:00:39:22
either the product variant directly
or the product group.
00:00:40:04 - 00:00:42:19
It's being used within.
00:00:43:26 - 00:00:45:24
So the first thing we're going to do
is navigate
00:00:45:24 - 00:00:55:28
to our production restrictions.
00:00:58:02 - 00:01:01:16
So rather than a series of tick boxes
for you to define the production
00:01:01:16 - 00:01:06:12
restriction on a per product basis, we've
introduced a much more global concept.
00:01:06:27 - 00:01:11:02
So you set up your restrictions
by heading to this screen here.
00:01:11:03 - 00:01:15:20
So the production restrictions in here,
you can create as many combinations
00:01:15:20 - 00:01:16:24
as you desire.
00:01:16:24 - 00:01:19:17
And then you apply this restriction
or whichever
00:01:19:24 - 00:01:24:00
restriction you want to either
the product or the product group level
00:01:26:23 - 00:01:28:20
to create a new production restriction.
00:01:28:20 - 00:01:32:02
We just go to add new record and define
00:01:32:02 - 00:01:38:17
the name, click insert
00:01:40:24 - 00:01:50:04
and then go to configure.
00:01:50:22 - 00:01:54:13
So production restrictions
effectively serve as sets of safe
00:01:54:14 - 00:01:57:15
delivery countdown configurations,
which can be applied
00:01:57:15 - 00:02:00:08
to multiple products at once,
if you wish to do so.
00:02:01:03 - 00:02:03:10
So going through some of the settings.
00:02:03:18 - 00:02:05:18
First off, we have the deadline hour.
00:02:06:01 - 00:02:09:13
So this is the deadline
for that particular order
00:02:09:19 - 00:02:14:06
that the customer is placing effectively
any orders placed after this hour.
00:02:14:06 - 00:02:16:08
So it's a 24 hour clock basis.
00:02:16:19 - 00:02:19:19
We'll have their execution
start on the following day.
00:02:19:28 - 00:02:23:22
So we'll add another day
to the delivery time.
00:02:23:27 - 00:02:26:10
So, for example, if I put 15 in here,
00:02:28:03 - 00:02:30:11
any order which comes in after 3 p.m.
00:02:30:18 - 00:02:33:07
will start on the following day.
00:02:37:09 - 00:02:40:01
Next, we have an execution offset.
00:02:40:12 - 00:02:43:02
So this is a value in number of days.
00:02:43:02 - 00:02:45:00
So whole number of days.
00:02:45:00 - 00:02:50:14
So a product may take 24 hours
to manufacture due to several components,
00:02:50:14 - 00:02:51:09
let's say.
00:02:51:09 - 00:02:55:21
So if you typed one into this field,
it would then add an additional day
00:02:55:27 - 00:02:57:28
for production
00:03:02:22 - 00:03:03:15
if desired.
00:03:03:15 - 00:03:06:17
You do have the ability
to specify execution
00:03:06:17 - 00:03:10:03
offset tiers as well.
00:03:12:17 - 00:03:15:04
So this allows you to increase or decrease
00:03:15:04 - 00:03:19:03
the execution offset based on the quantity
which has been ordered.
00:03:19:16 - 00:03:23:03
So multiple tiers can be specified
for each production restriction.
00:03:23:27 - 00:03:26:20
So for example, if I say
00:03:26:20 - 00:03:29:27
if we have a quantity of 100
and the offset,
00:03:29:27 - 00:03:35:13
there is going to be two days
instead of one going into that number.
00:03:40:06 - 00:03:41:22
We can insert as many tiers
00:03:41:22 - 00:03:44:02
as we like.
00:03:45:19 - 00:03:47:29
So then we can specify days to skip.
00:03:48:00 - 00:03:51:26
So these days are used to mark
which days you are not able to work
00:03:51:26 - 00:03:55:25
on the production of the output
such as weekends if the office is shut
00:03:56:16 - 00:03:59:20
out of daily delivery,
countdown estimation accordingly.
00:04:00:14 - 00:04:03:12
So I could say, for example, skip
Saturday and Skip Sunday.
00:04:03:27 - 00:04:06:17
Now, if an order is placed on Friday
00:04:07:00 - 00:04:11:13
with an execution offset of one day,
then it will not say.
00:04:11:13 - 00:04:13:20
It will be produced on Saturday.
00:04:13:20 - 00:04:18:03
It will skip those two days
and go to the following Monday.
00:04:20:03 - 00:04:21:29
We then have the ability to specify
00:04:21:29 - 00:04:24:03
from your configured calendars.
00:04:25:10 - 00:04:27:29
So calendars
and that configuration has been covered
00:04:27:29 - 00:04:30:22
in a different tutorial video.
00:04:30:22 - 00:04:34:12
Effectively, you're
now able to assign days on the calendar
00:04:34:22 - 00:04:37:19
wherein
you are not able to work on production.
00:04:37:25 - 00:04:40:19
So this could be public holidays or
00:04:40:19 - 00:04:43:18
maybe when your machinery is down
for servicing, for example,
00:04:44:14 - 00:04:47:17
by assigning a calendar
to the restriction, the restriction
00:04:47:17 - 00:04:53:15
calculation will now take all configured
calendar days into account.
00:04:55:17 - 00:04:56:00
And that's the
00:04:56:00 - 00:04:58:25
specification of the production
restriction completed.
00:04:59:12 - 00:05:05:22
We'll just go ahead and click Save.